Sanitary Sewer and Southern Avenue Interceptor Rehabilitation  

Project Owner: City of Mesa
Project Type:
Construction Manager at Risk
Construction Dates: 05/08 to 10/08

This project required the rehabilitation of wastewater pipelines at five different locations. Work included 16,289 LF of 12-to-21-inch sanitary sewer using CIPP rehabilitation. We also used slip-line rehabilitation for 2,725 LF of 27-inch RCP and 7,936 LF of 20-inch RCP sanitary sewer. The rehabilitation of 40 manholes was also included in the scope.


Achen-Garder-Mesa-SS-Southern-Ave-605px-1 

Achen-Gardner-Mesa-SS-Southern-Ave-290px-182px-2

Achen-Gardner-Mesa-SS-Southern-Ave-290px-182px-3